140911 Eblast L3 Mowing

Phase 3 is complete.

Phase 4 mowing is complete in Neighborhoods 40, 41, 42, 43, 46, 47, 48, and 62.

Next up for mowing will be Neighborhoods 44, 45, 21, and 19.

If the mowers cannot access the area, the line trimming crew will address those areas on Fridays.

Phase to Neighborhood list
Phase 1 Neighborhoods: 1 2 3 4 5 6 7 13 27 38   COMPLETED
Phase 2 Neighborhoods: 8 9 10 11 12 35 36 37 60   COMPLETED
Phase 3 Neighborhoods: 14 15 16 22 23 24 25 26 28 30 31 32 33 34   COMPLETED
Phase 4 Neighborhoods: 17 18 19 20 21 29 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 62

Here is the current level of mowing completion (in black):
















Compared to our last map: