160707 L3 Update

We’ve completed the following neighborhoods:

38, 27, 13, 7, 1, 6, 5, 4, 3, 2, 35, 9, 10, 12, 60, 37, 36, 8, 11, 33, and 24

These are the remaining neighborhoods and their anticipated order of completion:

Phase 1
25, 26, 14, 15, 34

Phase 2

16, 28, 22, 23, 30, 31, 32, 41, 40, 43, 42, 44, 45, 21, 29, 20, 19, 18, 17, 46, 62, 47, 48, 49, 50, 51, 52, 53, 54, 55, 56, 57, 58, 59


Posted by Carlton M Mathis at 5:38 AM
Email ThisBlogThis!Share to XShare to FacebookShare to Pinterest
Newer Post Older Post Home

Blog Archive

  • ►  2018 (5)
    • ►  October (1)
    • ►  July (2)
    • ►  June (2)
  • ►  2017 (13)
    • ►  November (3)
    • ►  October (5)
    • ►  July (2)
    • ►  June (2)
    • ►  May (1)
  • ▼  2016 (18)
    • ►  November (8)
    • ►  August (2)
    • ▼  July (3)
      • 160729 L3 Update We are just about midway thr...
      • 160714 L3 Update Phase 1 Has been completed. ...
      • 160707 L3 Update We’ve completed the following...
    • ►  June (5)
  • ►  2015 (15)
    • ►  November (4)
    • ►  October (3)
    • ►  September (1)
    • ►  August (1)
    • ►  July (4)
    • ►  June (2)
  • ►  2014 (7)
    • ►  September (1)
    • ►  August (1)
    • ►  July (1)
    • ►  June (1)
    • ►  May (1)
    • ►  April (2)
  • ►  2013 (24)
    • ►  November (2)
    • ►  October (2)
    • ►  September (3)
    • ►  August (1)
    • ►  July (1)
    • ►  May (3)
    • ►  April (3)
    • ►  March (1)
    • ►  February (2)
    • ►  January (6)

About Me

My photo
Carlton M Mathis
View my complete profile
Sun City Texas Community Association Facilities Department /. Awesome Inc. theme. Powered by Blogger.