As anticipated, the recent rains have stifled our progress. We have managed to complete Phase 1. We will begin Phase 2 in N16, and progress roughly in the order listed below.
Although the majority of this process can be handled by our mowers, there are some areas that are less accommodating and will need to be handled with line trimmers. The Line Trimmers can be up to 2 weeks behind the mowers. All cuttings will be left where they fall. This is a Fire Wise exercise only, and not for aesthetic, or any other purpose.
MOWING COMPLETED
Phase 1 Neighborhoods
38, 27, 13, 7, 4, 6, 1, 5, 3, 2, 35, 9, 10, 63, 60, 37, 36, 12, 8, 11, 33, 24, 25, 26, 15, 14, 34
MOWING REMAINING
Phase 2 Neighborhoods
16, 28, 22, 23, 30, 31, 32, 41, 40, 43, 42, 44, 45, 21, 29, 20, 19, 18, 17, 46, 62, 47, 48, 49, 50, 51, 52, 53, 54, 55, 56, 57, 58, 59