Thursday, October 5, 2017

171005 L3 Maintenance Update

We’re off to a pretty good start on our second round of mowing, with nearly half of Phase 1 completed. Hopefully the weather will continue to cooperate with us as we continue to move forward through the campus.

Although the majority of this process can handled by our mowers, there are some areas that are less accommodating and will need to be handled with line trimmers. The Line Trimmers can be up to 2 weeks behind the mowers. All cuttings will be left where they fall. This is a Fire Wise exercise only, and not for aesthetic, or any other purpose.

MOWING COMPLETED

Phase 1 Neighborhoods
38, 27, 13, 7, 1, 4, 6, 5, 3, 2, 35, 9, 10, 63

MOWING REMAINING

Phase 1
12, 60, 37, 36, 8, 11, 14, 33, 26, 25, 24, 15, 34

Phase 2

16, 28, 22, 23, 30, 31, 32, 41, 40, 43, 42, 44, 45, 21, 29, 20, 19, 18, 17, 46, 62, 47, 48, 53, 54, 56, 59, 58, 57, 55, 52, 51, 50, 49, 64