Wednesday, November 15, 2017

171117 L3 Maintenance Update
Mowing has been completed throughout the campus. There are some remaining areas where the mowers were not able to service that will need to be line trimmed. We are hoping to have these location addressed before next week’s holiday weekend, but please allow us up to 2 weeks to finish. Thank for your patience. We will begin anew in 2018 with a projected start around June 1st.  Have wonderful Thanksgiving weekend.

MOWING COMPLETED

Phase 1 Neighborhoods
38, 27, 13, 7, 1, 4, 6, 5, 3, 2, 35, 9, 10, 63, 12, 60, 37, 36, 8, 11, 14, 33, 26, 25, 24, 15, 34

Phase 2 Neighborhoods

16, 28, 22, 23, 30, 31, 32, 41, 40, 43, 42, 44, 45, 21, 29, 20, 19, 18, 17, 46, 62, 47, 48, 53, 54, 56, 59, 58, 57, 55, 52, 51, 50, 49, 64


Thursday, November 9, 2017

171110 L3 Maintenance Update

We had a little bit of precipitation this week which slowed us down a tad. Even so, we are more than 50% completed with Phase 2 maintenance.

Although the majority of this process can handled by our mowers, there are some areas that are less accommodating and will need to be handled with line trimmers. The Line Trimmers can be up to 2 weeks behind the mowers. All cuttings will be left where they fall. This is a Fire Wise exercise only, and not for aesthetic, or any other purpose.

MOWING COMPLETED

Phase 1 Neighborhoods
38, 27, 13, 7, 1, 4, 6, 5, 3, 2, 35, 9, 10, 63, 12, 60, 37, 36, 8, 11, 14, 33, 26, 25, 24, 15, 34

Phase 2 Neighborhoods
16, 28, 22, 23, 30, 31, 32, 41, 40, 43, 42, 44, 45, 21, 29, 20, 19, 18, 17, 46, 62, 47, 48, 53, 54, 56, 59

MOWING REMAINING

Phase 2 Neighborhoods

58, 57, 55, 52, 51, 50, 49, 64


Wednesday, November 1, 2017

171103 L3 Maintenance Update

We had a little bit of precipitation this week which slowed us down a tad. Even so, we are nearly 50% completed with Phase 2 maintenance.

Although the majority of this process can handled by our mowers, there are some areas that are less accommodating and will need to be handled with line trimmers. The Line Trimmers can be up to 2 weeks behind the mowers. All cuttings will be left where they fall. This is a Fire Wise exercise only, and not for aesthetic, or any other purpose.

MOWING COMPLETED

Phase 1 Neighborhoods
38, 27, 13, 7, 1, 4, 6, 5, 3, 2, 35, 9, 10, 63, 12, 60, 37, 36, 8, 11, 14, 33, 26, 25, 24, 15, 34

Phase 2 Neighborhoods
16, 28, 22, 23, 30, 31, 32, 41, 40, 43, 42, 44, 45, 21, 29, 20, 19, 18, 17

MOWING REMAINING

Phase 2 Neighborhoods

46, 62, 47, 48, 53, 54, 56, 59, 58, 57, 55, 52, 51, 50, 49, 64