171103 L3 Maintenance Update

We had a little bit of precipitation this week which slowed us down a tad. Even so, we are nearly 50% completed with Phase 2 maintenance.

Although the majority of this process can handled by our mowers, there are some areas that are less accommodating and will need to be handled with line trimmers. The Line Trimmers can be up to 2 weeks behind the mowers. All cuttings will be left where they fall. This is a Fire Wise exercise only, and not for aesthetic, or any other purpose.

MOWING COMPLETED

Phase 1 Neighborhoods
38, 27, 13, 7, 1, 4, 6, 5, 3, 2, 35, 9, 10, 63, 12, 60, 37, 36, 8, 11, 14, 33, 26, 25, 24, 15, 34

Phase 2 Neighborhoods
16, 28, 22, 23, 30, 31, 32, 41, 40, 43, 42, 44, 45, 21, 29, 20, 19, 18, 17

MOWING REMAINING

Phase 2 Neighborhoods

46, 62, 47, 48, 53, 54, 56, 59, 58, 57, 55, 52, 51, 50, 49, 64