Thursday, October 15, 2015

151015 Eblast

Round 2 of the Level 3 Maintenance commenced on Monday, October 5th. The property is divided into 3 sections, or phases, that are numbered in the order which we will proceed. This map shows the different sections as well as the path of the crew through completion.


We began in neighborhood 53, working our way down through the neighborhoods on the north and east side of Pedernales, in the following order: 54, 56, and 59. We will then cross Pedernales, and work the south and west side of the street accordingly: 58, 57, 55, 52, 51, and 50. Jumping back across Pedernales we will continue with 47, 62, and 46.

Neighborhoods 51-57 and 59 have been mowed. 53, 54, 56 and 59 have been mowed and line trimmed.
We’re moving at a “good clip” (Pun intended).  


Friday, September 4, 2015

150902 Native Area Maintenance

The first pass of the Native Area Mowing has been completed, and we are working on cleaning out the drainage ditches and their respective outfalls. We expect to begin round two of the maintenance in October.

Thursday, August 6, 2015


Phase 2 is now complete. We have started Phase 3 in Neighborhood 14, and have finished portions of Neighborhood 24 and 33. We will continue through the remaining neighborhoods tentatively as follows:

25, 26, 15, 34, 16, 22, 23, 28, 30, 31, and 32.

As a reminder, we are rotating where we start our maintenance program every year. Those neighborhoods that were at the end of the program this year will be at the beginning next year. This is better for the landscape, is fair to all the residents.

We hope to have all mowing completed by the end of August, almost 6 weeks ahead of when we finished last year. The second pass will most likely begin at the end of September, or early October.

The line trimming crew is no more than a week behind, and usually occurs on Fridays.


This map illustrates our progress so far:


Thursday, July 30, 2015


My apologies for the lack of an update last week. We had a substantial waterline break underneath Sun City Blvd that demanded my attention. We are currently in the vicinity of NH 5 and working the areas around the LHGC fairways for Holes 10, 11, 12, 13 and 18. From there we will move to neighborhoods 4, 7, 13, 27, and 38. I am hoping to have these remaining neighborhoods in Phase 2 mowed by August 7th, at which point we will begin Phase 3 in neighborhood 33.

The line trimming crew has made great progress catching up with the mowers and are no more than a week behind.


This map illustrates our progress so far:



Thursday, July 16, 2015

150716 L3 Update

The Phase 2 mowing has made it to Berry Creek. On the north side of the creek we will begin in NH2 and progress through to neighborhoods 3, 5, 6, 4, 7, 1, 13, 27, and 38.

The line trimming crew will complete Phase 1 today and begin working their way up Del Webb to Williams Drive.



This map illustrates our progress so far:


Wednesday, July 8, 2015

150708 L3 Update

The Phase 2 mowing is currently in Neighborhood 10 and are working their way along the inbound side of Del Webb toward Berry Creek, picking up neighborhoods 9 and 35. On the north side of the creek we will begin in NH2 and progress toward through neighborhoods 3, 5, 6, 4, 7, 1, 13, 27, and 38.

Due to the holiday, no major progress has been made on the line trimming front. The line trimming crew is nearly complete with Phase 1 and only have neighborhoods 40, 41, 42, 44, 45, 21, 19, 29, 20, 18, and 17 to finish. We expect them to be through with Phase 1 and into Phase 2 by end of the day Friday July 10th.


This map illustrates our progress so far:


Thursday, July 2, 2015

150702 L3 Update

The Phase 2 mowing is currently in Neighborhood 12 and will finish 37 and 60 next. We will cross Del Webb, beginning at Neighborhood 10 and working their way back toward Berry Creek, picking up neighborhoods 9 and 35 along the way.

The line trimming crew is nearly complete with Phase 1 and only have neighborhoods 40, 41, 42, 44, 45, 21, 19, 29, 20, 18, and 17 to finish. We expect them to be through with Phase 1 and into Phase 2 by end of the day Friday July 10th.


This map illustrates our progress so far: