150626 L3 Update
Phase 1 mowing
has been completed, and we will begin Phase 2 mowing in Neighborhood 11 on Monday, June 29th. Phase 2
mowing will proceed as follows 11, 8, 36, 12, 37, and 60 to start with.
The Line Trimming Crew will continue to make progress in
Phase 1, and should begin Phase 2 next Friday. As a reminder, we run our full
complement of mowing equipment Monday through Thursday, and all of our line
trimmers on Friday. The line trimmers can be up to 2 weeks behind.