150702 L3 Update
The Phase 2 mowing is currently in Neighborhood 12 and will
finish 37 and 60 next. We will cross Del Webb, beginning at Neighborhood 10 and
working their way back toward Berry Creek, picking up neighborhoods 9 and 35
along the way.
The line trimming crew is nearly complete with Phase 1 and
only have neighborhoods 40, 41, 42, 44, 45, 21, 19, 29, 20, 18, and 17 to
finish. We expect them to be through with Phase 1 and into Phase 2 by end of
the day Friday July 10th.
This map illustrates our progress so far: