Thursday, July 30, 2015


My apologies for the lack of an update last week. We had a substantial waterline break underneath Sun City Blvd that demanded my attention. We are currently in the vicinity of NH 5 and working the areas around the LHGC fairways for Holes 10, 11, 12, 13 and 18. From there we will move to neighborhoods 4, 7, 13, 27, and 38. I am hoping to have these remaining neighborhoods in Phase 2 mowed by August 7th, at which point we will begin Phase 3 in neighborhood 33.

The line trimming crew has made great progress catching up with the mowers and are no more than a week behind.


This map illustrates our progress so far: