150708 L3 Update
The Phase 2 mowing is currently in Neighborhood 10 and are
working their way along the inbound side of Del Webb toward Berry Creek, picking
up neighborhoods 9 and 35. On the north side of the creek we will begin in NH2
and progress toward through neighborhoods 3, 5, 6, 4, 7, 1, 13, 27, and 38.
Due to the holiday, no major progress has been made on the
line trimming front. The line trimming crew is nearly complete with Phase 1 and
only have neighborhoods 40, 41, 42, 44, 45, 21, 19, 29, 20, 18, and 17 to
finish. We expect them to be through with Phase 1 and into Phase 2 by end of
the day Friday July 10th.
This map illustrates our progress so far: