Thursday, November 12, 2015

151112 Native Area Maintenance Eblast

For the most part the weather has been cooperative with the second maintenance round this year.

The mowing and line trimming have been completed in the following neighborhoods:
8 - 12, 17 -21, 29, 35-37, and 40 – 60.

We are currently working through neighborhoods 1 -7. Neighborhoods 13, 27, and 38 will follow shortly.

The remaining neighborhoods are in Phase 3, and we will begin them in a couple of weeks, starting with neighborhoods 24, 25, 26, and 33.


Here is the current map of our progress: