Thursday, November 19, 2015


The Phase 2 area is nearly complete, and we are hoping to begin Phase 3 as early as next week, weather permitting.

The mowing and line trimming have been completed in the following neighborhoods:
1-3, 5-6, 8 - 12, 17 -21, 29, 35-37, and 40 – 60.

We are currently working through neighborhood 4, 7, and 13, neighborhoods 27, and 38 will follow shortly.

The remaining neighborhoods are in Phase 3, and we will begin them in a couple of weeks, starting with neighborhoods 24, 25, 26, and 33.


Here is the current map of our progress: