170607 Level 3 Maintenance Update
Round 1, Phase 1, week 1 has us at a really good pace right
out of the gate. We will be mowing in the neighborhoods south of Berry Creek
next week.
Although the majority of this
process can handled by our mowers, there are some areas that are less
accommodating and will need to be handled with line trimmers. The Line
Trimmers can be up to 2 weeks behind the mowers. All cuttings will be left
where they fall. This is a Fire Wise exercise only, and not for aesthetic, or
any other purpose.
MOWING COMPLETED
Phase 1 Neighborhoods
38, 27, 13, 7, 4, 6, 1, 5, 3, 2
MOWING REMAINING
Phase 1
Neighborhoods
35, 9, 10, 63, 12, 60, 37, 36, 8, 11, 14, 33, 26, 25, 24,
15, 34
Phase 2
Neighborhoods
16, 28, 22, 23, 30, 31, 32, 41, 40, 43, 42, 44, 45, 21, 29,
20, 19, 18, 17, 46, 62, 47, 48, 53, 54, 56, 59, 58, 57, 55, 52, 51, 50, 49, 64