Thursday, June 22, 2017

170622 Level 3 Maintenance Update

My apologies for missing last week’s update, I had to spend the week in Boerne for one of my license recertifications. The crew however did not take the week off, and is continuing at a record pace. We are expecting to have Phase 1 completed by the end of June.

Although the majority of this process can handled by our mowers, there are some areas that are less accommodating and will need to be handled with line trimmers. The Line Trimmers can be up to 2 weeks behind the mowers. All cuttings will be left where they fall. This is a Fire Wise exercise only, and not for aesthetic, or any other purpose.

MOWING COMPLETED

Phase 1 Neighborhoods
38, 27, 13, 7, 4, 6, 1, 5, 3, 2, 35, 9, 10, 63, 12, 60, 37, 36, 8, 11, 14, 33, 24

MOWING REMAINING

Phase 1 Neighborhoods
26, 25, 15, 34

Phase 2 Neighborhoods

16, 28, 22, 23, 30, 31, 32, 41, 40, 43, 42, 44, 45, 21, 29, 20, 19, 18, 17, 46, 62, 47, 48, 53, 54, 56, 59, 58, 57, 55, 52, 51, 50, 49, 64