My apologies for missing last week’s update, I had to spend the week
in Boerne for one of my license recertifications. The crew however did not
take the week off, and is continuing at a record pace. We are expecting to have
Phase 1 completed by the end of June.
Although the majority of this process can
handled by our mowers, there are some areas that are less accommodating and
will need to be handled with line trimmers. The Line Trimmers can be up
to 2 weeks behind the mowers. All cuttings will be left where they fall. This
is a Fire Wise exercise only, and not for aesthetic, or any other purpose.
MOWING COMPLETED
Phase 1 Neighborhoods
38, 27, 13, 7, 4, 6, 1, 5, 3, 2, 35, 9, 10, 63, 12, 60, 37, 36, 8, 11,
14, 33, 24
MOWING REMAINING
Phase 1 Neighborhoods
26, 25, 15, 34
Phase 2 Neighborhoods
16, 28, 22, 23, 30, 31, 32, 41, 40, 43, 42, 44, 45, 21, 29, 20, 19,
18, 17, 46, 62, 47, 48, 53, 54, 56, 59, 58, 57, 55, 52, 51, 50, 49, 64