180621 Level 3 Maintenance Update
We had to start a
little bit later this year, but Round 1, Phase 1, Week 1 has us at a really
good pace right out of the gate. We will be mowing in the neighborhoods south
of Berry Creek next week.
Although the majority of this process can handled by our mowers, there
are some areas that are less accommodating and will need to be handled with
line trimmers. The Line Trimmers can be up to 2 weeks behind the mowers.
All cuttings will be left where they fall. This is a Fire Wise exercise only,
and not for aesthetic, or any other purpose.
MOWING COMPLETED
Phase 1 Neighborhoods
38, 27, 13, 7, 4, 6, 1, 5, 3, 2
MOWING REMAINING
Phase 1 Neighborhoods
35, 9, 10, 63, 12, 60,
37, 36, 8, 11, 14, 33, 26, 25, 24, 15, 34
Phase 2 Neighborhoods
16, 28, 22, 23, 30, 31,
32, 41, 40, 43, 42, 44, 45, 21, 29, 20, 19, 18, 17, 46, 62, 47, 48, 53, 54, 56,
59, 58, 57, 55, 52, 51, 50, 49, 64