Thursday, June 28, 2018


180628 Level 3 Maintenance Update

Week 2 of our Level 3 maintenance has more than halfway completed with Phase 1. This Friday we will have the whole team on line trimmers in an effort to get caught up to the mowers.

Although the majority of this process can handled by our mowers, there are some areas that are less accommodating and will need to be handled with line trimmers. The Line Trimmers can be up to 2 weeks behind the mowers. All cuttings will be left where they fall. This is a Fire Wise exercise only, and not for aesthetic, or any other purpose.

MOWING COMPLETED

Phase 1 Neighborhoods
38, 27, 13, 7, 4, 6, 1, 5, 3, 2, 35, 9, 10, 63, 12, 60, 37, 36

MOWING REMAINING

Phase 1 Neighborhoods
8, 11, 14, 33, 26, 25, 24, 15, 34

Phase 2 Neighborhoods
16, 28, 22, 23, 30, 31, 32, 41, 40, 43, 42, 44, 45, 21, 29, 20, 19, 18, 17, 46, 62, 47, 48, 53, 54, 56, 59, 58, 57, 55, 52, 51, 50, 49, 64