180705 Level 3 Maintenance Update

Week 3 of our Level 3 maintenance has us in NH24.  Progress has been a little slower this week due the holiday and recent rains.

Although the majority of this process can handled by our mowers, there are some areas that are less accommodating and will need to be handled with line trimmers. The Line Trimmers can be up to 2 weeks behind the mowers. All cuttings will be left where they fall. This is a Fire Wise exercise only, and not for aesthetic, or any other purpose.

MOWING COMPLETED

Phase 1 Neighborhoods
38, 27, 13, 7, 4, 6, 1, 5, 3, 2, 35, 9, 10, 63, 12, 60, 37, 36, 8, 11, 14, 33

MOWING REMAINING

Phase 1 Neighborhoods
26, 25, 24, 15, 34

Phase 2 Neighborhoods
16, 28, 22, 23, 30, 31, 32, 41, 40, 43, 42, 44, 45, 21, 29, 20, 19, 18, 17, 46, 62, 47, 48, 53, 54, 56, 59, 58, 57, 55, 52, 51, 50, 49, 64