Friday, June 10, 2016

160609 L3 Update

The Level 3 Maintenance is moving along and we’re starting to get into a groove. The team is mowing and line trimming a path up to 30 feet behind the resident property lines per Fire Wise guidelines.

We’ve completed the following neighborhoods:
38, 27, 13, 7, and 4

These are the remaining neighborhoods and their projected order of completion:

Phase 1
1, 6, 5, 3, 2, 35, 9, 10, 12, 60, 37, 36, 8, 11, 34, 15, 14, 33, 26, 25, 24
Phase 2

16, 28, 22, 23, 30, 31, 32, 41, 40, 43, 42, 44, 45, 21, 29, 20, 19, 18, 17, 46, 62, 47, 48, 49, 50, 51, 52, 53, 54, 55, 56, 57, 58, 59