Tuesday, May 30, 2017

170530 L3 Maintenance Plan

Weather permitting, we are planning to begin our bi-annual maintenance of the Native Common areas the first full week of June. Please find below the proposed neighborhood order of maintenance.

Although the majority of this process can handled by our mowers, there are some areas that are less accommodating and will need to be handled with line trimmers. The Line Trimmers can be up to 2 weeks behind the mowers. All cuttings will be left where they fall. This is a Fire Wise exercise only, and not for aesthetic, or any other purpose.

Phase 1
38, 27, 13, 7, 1, 4, 6, 5, 3, 2, 35, 9, 10, 63, 12, 60, 37, 36, 8, 11, 14, 33, 26, 25, 24, 15, 34
Phase 2

16, 28, 22, 23, 30, 31, 32, 41, 40, 43, 42, 44, 45, 21, 29, 20, 19, 18, 17, 46, 62, 47, 48, 53, 54, 56, 59, 58, 57, 55, 52, 51, 50, 49, 64