Thursday, October 25, 2018


181025 Level 3 Maintenance Update

Normally we would be much further along at this point, but the recent rains have retarded our progress. We will continue to press on in between wet weather events.

Although the majority of this process can handled by our mowers, there are some areas that are less accommodating, and will need to be handled with line trimmers. The Line Trimmers can be up to 2 weeks behind the mowers. All cuttings will be left where they fall. This is a Fire Wise exercise only, and not for aesthetic, or any other purpose.

MOWING COMPLETED

Phase 1 Neighborhoods
38, 27, 13, 7, 4, 6, 1, 5, 3, 2, 35, 9, 10, 63

MOWING REMAINING

Phase 1 Neighborhoods
12, 60, 37, 36, 8, 11, 14, 33, 26, 25, 24, 15, 34

Phase 2 Neighborhoods
16, 28, 22, 23, 30, 31, 32, 41, 40, 43, 42, 44, 45, 21, 29, 20, 19, 18, 17, 46, 62, 47, 48, 53, 54, 56, 59, 58, 57, 55, 52, 51, 50, 49, 64, 81, 82



Wednesday, July 18, 2018


180718 Level 3 Maintenance Update

Phase 2 mowing has been completed through NH45, and is beginning NH21.

Although the majority of this process can handled by our mowers, there are some areas that are less accommodating and will need to be handled with line trimmers. The Line Trimmers can be up to 2 weeks behind the mowers. All cuttings will be left where they fall. This is a Fire Wise exercise only, and not for aesthetic, or any other purpose.

MOWING COMPLETED

Phase 1 Neighborhoods
38, 27, 13, 7, 4, 6, 1, 5, 3, 2, 35, 9, 10, 63, 12, 60, 37, 36, 8, 11, 14, 33, 26, 25, 24, 15, 34

Phase 2 Neighborhoods
16, 28, 22, 23, 30, 31, 32, 41, 40, 43, 42, 44, 45

MOWING REMAINING

Phase 2 Neighborhoods

21, 29, 20, 19, 18, 17, 46, 62, 47, 48, 53, 54, 56, 59, 58, 57, 55, 52, 51, 50, 49, 64




Thursday, July 5, 2018


180705 Level 3 Maintenance Update

Week 3 of our Level 3 maintenance has us in NH24.  Progress has been a little slower this week due the holiday and recent rains.

Although the majority of this process can handled by our mowers, there are some areas that are less accommodating and will need to be handled with line trimmers. The Line Trimmers can be up to 2 weeks behind the mowers. All cuttings will be left where they fall. This is a Fire Wise exercise only, and not for aesthetic, or any other purpose.

MOWING COMPLETED

Phase 1 Neighborhoods
38, 27, 13, 7, 4, 6, 1, 5, 3, 2, 35, 9, 10, 63, 12, 60, 37, 36, 8, 11, 14, 33

MOWING REMAINING

Phase 1 Neighborhoods
26, 25, 24, 15, 34

Phase 2 Neighborhoods
16, 28, 22, 23, 30, 31, 32, 41, 40, 43, 42, 44, 45, 21, 29, 20, 19, 18, 17, 46, 62, 47, 48, 53, 54, 56, 59, 58, 57, 55, 52, 51, 50, 49, 64



Thursday, June 28, 2018


180628 Level 3 Maintenance Update

Week 2 of our Level 3 maintenance has more than halfway completed with Phase 1. This Friday we will have the whole team on line trimmers in an effort to get caught up to the mowers.

Although the majority of this process can handled by our mowers, there are some areas that are less accommodating and will need to be handled with line trimmers. The Line Trimmers can be up to 2 weeks behind the mowers. All cuttings will be left where they fall. This is a Fire Wise exercise only, and not for aesthetic, or any other purpose.

MOWING COMPLETED

Phase 1 Neighborhoods
38, 27, 13, 7, 4, 6, 1, 5, 3, 2, 35, 9, 10, 63, 12, 60, 37, 36

MOWING REMAINING

Phase 1 Neighborhoods
8, 11, 14, 33, 26, 25, 24, 15, 34

Phase 2 Neighborhoods
16, 28, 22, 23, 30, 31, 32, 41, 40, 43, 42, 44, 45, 21, 29, 20, 19, 18, 17, 46, 62, 47, 48, 53, 54, 56, 59, 58, 57, 55, 52, 51, 50, 49, 64




180621 Level 3 Maintenance Update

We had to start a little bit later this year, but Round 1, Phase 1, Week 1 has us at a really good pace right out of the gate. We will be mowing in the neighborhoods south of Berry Creek next week.

Although the majority of this process can handled by our mowers, there are some areas that are less accommodating and will need to be handled with line trimmers. The Line Trimmers can be up to 2 weeks behind the mowers. All cuttings will be left where they fall. This is a Fire Wise exercise only, and not for aesthetic, or any other purpose.

MOWING COMPLETED

Phase 1 Neighborhoods
38, 27, 13, 7, 4, 6, 1, 5, 3, 2

MOWING REMAINING

Phase 1 Neighborhoods
35, 9, 10, 63, 12, 60, 37, 36, 8, 11, 14, 33, 26, 25, 24, 15, 34

Phase 2 Neighborhoods
16, 28, 22, 23, 30, 31, 32, 41, 40, 43, 42, 44, 45, 21, 29, 20, 19, 18, 17, 46, 62, 47, 48, 53, 54, 56, 59, 58, 57, 55, 52, 51, 50, 49, 64



Wednesday, November 15, 2017

171117 L3 Maintenance Update
Mowing has been completed throughout the campus. There are some remaining areas where the mowers were not able to service that will need to be line trimmed. We are hoping to have these location addressed before next week’s holiday weekend, but please allow us up to 2 weeks to finish. Thank for your patience. We will begin anew in 2018 with a projected start around June 1st.  Have wonderful Thanksgiving weekend.

MOWING COMPLETED

Phase 1 Neighborhoods
38, 27, 13, 7, 1, 4, 6, 5, 3, 2, 35, 9, 10, 63, 12, 60, 37, 36, 8, 11, 14, 33, 26, 25, 24, 15, 34

Phase 2 Neighborhoods

16, 28, 22, 23, 30, 31, 32, 41, 40, 43, 42, 44, 45, 21, 29, 20, 19, 18, 17, 46, 62, 47, 48, 53, 54, 56, 59, 58, 57, 55, 52, 51, 50, 49, 64


Thursday, November 9, 2017

171110 L3 Maintenance Update

We had a little bit of precipitation this week which slowed us down a tad. Even so, we are more than 50% completed with Phase 2 maintenance.

Although the majority of this process can handled by our mowers, there are some areas that are less accommodating and will need to be handled with line trimmers. The Line Trimmers can be up to 2 weeks behind the mowers. All cuttings will be left where they fall. This is a Fire Wise exercise only, and not for aesthetic, or any other purpose.

MOWING COMPLETED

Phase 1 Neighborhoods
38, 27, 13, 7, 1, 4, 6, 5, 3, 2, 35, 9, 10, 63, 12, 60, 37, 36, 8, 11, 14, 33, 26, 25, 24, 15, 34

Phase 2 Neighborhoods
16, 28, 22, 23, 30, 31, 32, 41, 40, 43, 42, 44, 45, 21, 29, 20, 19, 18, 17, 46, 62, 47, 48, 53, 54, 56, 59

MOWING REMAINING

Phase 2 Neighborhoods

58, 57, 55, 52, 51, 50, 49, 64